Construction of a reading garden, Bellerose Playground, adjacent to P.S. 133, 249th Street between 85th Avenue and 86th Avenue, Bellerose Manor, Queens

Queens · DPR · Landscape architecture · Final · Approved

Construction
Construction
Public/Private
Public
First Seen
2020-06-22
Last Seen
2020-06-22

Stage Progression

Conceptual
Preliminary
2020-12-14
Final
2020-12-14

Review History

DateCertificateStageActionResultSourceDocs
2020-06-22 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Construction of a reading garden, Bellerose Playground, adjacent to P.S. 133, 24… Preliminary and Final 2020-12-14 2020-12-14