Construction of Bridge Park South, including an extension of the Harlem River Greenway, Exterior Street, The High Bridge, the East River, and the Alexander Hamilton Bridge, Bronx

Bronx · DPR · Landscape architecture · Final · Approved with conditions

Construction
Construction
Public/Private
Public
First Seen
2020-03-30
Last Seen
2020-03-30

Stage Progression

Conceptual
Preliminary
2021-02-22
Final
2025-08-18
Preliminary → Final: 1638 days
Result: Approved with conditions

Review History

DateCertificateStageActionResultSourceDocs
2020-03-30 Commented annual_report_api Minutes

Meeting Videos

Public Design Commission Meeting March 30, 2020 (2020-03-30)

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Construction of Bridge Park South, including an extension of the Harlem River Gr… Preliminary 2021-02-22 2021-02-22
Construction of Bridge Park South, including an extension of the Harlem River Gr… Final 2025-08-18 2025-08-18
Subscribe to Updates Back to Projects