Construction of an addition and installation of rooftop mechanical equipment, George R. Vierno Center, 09-09 Hazen Street, Rikers Island, Bronx

Bronx · DOC · Architecture · Final · Approved

City Council
22
Community Board
Q1
Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2020-01-21
Last Seen
2020-01-21

Stage Progression

Conceptual
Preliminary
2020-01-21
Final
2020-01-21

Review History

DateCertificateStageActionResultSourceDocs
2020-01-20 Approved annual_report_api
2020-01-21 27326 Preliminary and Final agenda_pdf Minutes
2020-01-21 27326 Preliminary and Final Calendared for Consent monthly_review_api Minutes

Related Projects

Other projects at this site (2)
TitleStageAgencyFirst Seen
Installation of rooftop equipment, George R. Vierno Center, 09-09 Hazen Street, …
Installation of methane blowers, George R. Vierno Center, 09-09 Hazen Street, Ri… Preliminary and Final DOC 2018-06-11