Stage Progression

Conceptual
2011-01-10
Preliminary
2011-07-18
Final
2020-02-18
Conceptual → Preliminary: 189 days
Preliminary → Final: 3137 days
Result: Approved with conditions

Review History

DateCertificateStageActionResultSourceDocs
2019-09-16 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (3)
TitleStageFirst SeenLast Seen
Installation of Inhale/Exhale and Independent Lines by Monika Goetz, 122 Communi…
Installation of Inhale/Exhale and Independent Lines by Monika Goetz, 122 Communi…
Installation of Inhale/Exhale and Independent Lines by Monika Goetz, 122 Communi… Final 2020-03-30 2020-03-30
Other projects at this site (1)
TitleStageAgencyFirst Seen
Rehabilitation of a façade, 122 Community Center, 150 First Avenue, Manhattan Preliminary and Final DDC 2024-06-02
Subscribe to Updates Back to Projects