Construction of a utility enclosure for electric vehicle charging equipment, White Plains Road Municipal Parking Field, 2071 White Plains Road, Bronx

Bronx · DOT · Architecture · Final · Approved

City Council
13
Community Board
11
Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2019-08-12
Last Seen
2019-08-12

Stage Progression

Conceptual
Preliminary
2019-08-12
Final
2023-09-18
Preliminary → Final: 1498 days

Review History

DateCertificateStageActionResultSourceDocs
2019-08-12 27161 Preliminary agenda_pdf Minutes
2019-08-12 Approved with conditions annual_report_api Minutes
2019-08-12 27161 Preliminary Calendared for Consent monthly_review_api Minutes

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Construction of a utility enclosure for electric vehicle charging equipment, Whi… Final 2023-09-18 2023-09-18
Other projects at this site (2)
TitleStageAgencyFirst Seen
Installation of electric vehicle chargers (PowerCharge) including an electrical … Preliminary and Final DOT 2024-12-16
Minor modifications to the installation of electric vehicle chargers (PowerCharg… Amended Final DOT 2025-02-24