Installation of rooftop mechanical equipment, Main Building, Oakwood Beach Wastewater Resource Recovery Facility, 751 Mill Road, Staten Island

Staten Island · DEP · Building systems & Modifications · Final · Approved

City Council
50
Community Board
2
Construction
Installation of specific elements
Public/Private
Public
Review Cycles
1
First Seen
2019-08-12
Last Seen
2019-08-12

Stage Progression

Conceptual
Preliminary
2019-08-12
Final
2019-08-12

Review History

DateCertificateStageActionResultSourceDocs
2019-08-12 27156 Preliminary and Final agenda_pdf Minutes
2019-08-12 Approved annual_report_api Minutes
2019-08-12 27156 Preliminary and Final Calendared for Consent monthly_review_api Minutes

Related Projects

Other projects at this site (2)
TitleStageAgencyFirst Seen
Installation of rooftop equipment and chemical addition equipment, Main Building… Preliminary and Final DEP 2021-11-15
Installation of rooftop mechanical equipment and skylights, Main Building, Oakwo… Preliminary and Final DEP 2026-01-08
Subscribe to Updates Back to Projects