Reconstruction of a portion of Michaelis-Bayswater Park, Bay 32nd Street, Beach Channel Drive, Beach 35th Street, and Norton Avenue, Far Rockaway, Queens

Queens · DPR · Landscape architecture · Final · Approved

Construction
Reconstruction
Public/Private
Public
First Seen
2019-07-15
Last Seen
2019-07-15

Stage Progression

Conceptual
Preliminary
2019-10-21
Final
2021-12-13
Preliminary → Final: 784 days

Review History

DateCertificateStageActionResultSourceDocs
2019-07-15 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Reconstruction of a portion of Michaelis-Bayswater Park, Bay 32nd Street, Beach … Preliminary 2019-10-21 2019-10-21
Reconstruction of a portion of Michaelis-Bayswater Park, Bay 32nd Street, Beach … Final 2021-12-13 2021-12-13
Subscribe to Updates Back to Projects