Construction of an entrance, outlook, and adjacent site work, Snug Harbor Cultural Center & Botanical Garden, Kissel Avenue at Linden Street, Staten Island

Staten Island · DCLA · Landscape architecture · Final · Approved

City Council
49
Community Board
1
Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2019-07-15
Last Seen
2019-07-15

Stage Progression

Conceptual
Preliminary
2019-07-15
Final
2019-08-12
Preliminary → Final: 28 days

Review History

DateCertificateStageActionResultSourceDocs
2019-07-15 27102 Preliminary agenda_pdf Minutes
2019-07-15 Approved annual_report_api Minutes
2019-07-15 27102 Preliminary Calendared for Consent monthly_review_api Minutes

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Construction of an entrance, outlook, and adjacent site work, Snug Harbor Cultur… Final 2019-08-12 2019-08-12
Subscribe to Updates Back to Projects