Reconstruction of a plaza (Canal Street Triangle) as part of the Gateways to Chinatown program, Walker Street, Baxter Street, and Canal Street, Manhattan

Manhattan · DOT · Landscape architecture · Final · Approved with conditions

Construction
Reconstruction
Public/Private
Public
First Seen
2019-08-12
Last Seen
2020-12-14

Stage Progression

Conceptual
Preliminary
2021-03-22
Final
2021-05-24
Preliminary → Final: 63 days
Result: Approved with conditions

Review History

DateCertificateStageActionResultSourceDocs
2019-08-12 Commented annual_report_api Minutes
2020-12-14 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Reconstruction of a plaza (Canal Street Triangle) as part of the Gateways to Chi… Preliminary 2021-03-22 2021-03-22
Reconstruction of a plaza (Canal Street Triangle) as part of the Gateways to Chi… Final 2021-05-26 2021-05-26