Construction of the esplanade, Phase V, East River Waterfront between Peck Slip and Catherine Slip, Manhattan
Manhattan · EDC · Landscape architecture · Approved with conditions
- City Council
- 1
- Community Board
- 1 & 3
- Construction
- Construction
- Public/Private
- Public
- Review Cycles
- 1
- First Seen
- 2019-06-17
- Last Seen
- 2019-06-17
Stage Progression
Conceptual
—
Preliminary
2019-06-17
Final
—
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2019-05-20 | Commented | annual_report_api | ||||
| 2019-06-17 | 27096 | Preliminary | agenda_pdf | Minutes | ||
| 2019-06-17 | Approved with conditions | annual_report_api | Minutes | |||
| 2019-06-17 | 27096 | Preliminary | Calendared for Consent | monthly_review_api | Minutes |