Installation of interpretive signage for an educational compost facility, Queens Botanical Garden, 43-50 Main Street, Flushing, Queens

Queens · DCLA · Signage · Final · Approved

City Council
20
Community Board
7
Construction
Installation of specific elements
Public/Private
Public
Review Cycles
2
First Seen
2019-03-18
Last Seen
2019-03-18

Stage Progression

Conceptual
Preliminary
2019-03-18
Final
2019-03-18

Review History

DateCertificateStageActionResultSourceDocs
2019-02-19 Commented annual_report_api Minutes
2019-03-18 26968 Preliminary and Final agenda_pdf Minutes
2019-03-18 Approved annual_report_api Minutes
2019-03-18 26968 Preliminary and Final Calendared for Consent monthly_review_api Minutes

Related Projects

Other projects at this site (3)
TitleStageAgencyFirst Seen
Installation of a pavilion and adjacent site work, Queens Botanical Garden, 43-5… DCLA 2018-05-14
Construction of an educational compost facility and adjacent site work, Queens B… Preliminary DCLA 2018-06-11
Construction of an educational compost facility and adjacent site work, Queens B… Final DPR 2018-10-15