Construction of an ADA ramp and stairs, 37 West 93rd Street, Manhattan

Manhattan · DOT · Building systems & Modifications · Final · Approved

City Council
6
Community Board
7
Construction
Construction
Public/Private
Private
Review Cycles
1
First Seen
2018-12-17
Last Seen
2018-12-17

Stage Progression

Conceptual
Preliminary
2018-12-17
Final
2019-01-22
Preliminary → Final: 36 days

Review History

DateCertificateStageActionResultSourceDocs
2018-12-17 26876 Preliminary agenda_pdf Minutes
2018-12-17 Approved annual_report_api Minutes
2018-12-17 26876 Preliminary Calendared for Consent monthly_review_api Minutes

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Construction of an ADA ramp and stairs, 37 West 93rd Street, Manhattan Final 2019-01-22 2019-01-22
Subscribe to Updates Back to Projects