Rehabilitation of a sanitation garage and adjacent site work, Districts 11 and 13, 75-05 Winchester Boulevard, Queens Village, Queens

Queens · DDC · Architecture · Final · Approved with conditions

City Council
23
Community Board
11
Construction
Rehabilitation
Public/Private
Public
Review Cycles
1
First Seen
2018-09-17
Last Seen
2019-09-16

Stage Progression

Conceptual
Preliminary
2018-09-17
Final
2019-11-18
Preliminary → Final: 427 days
Result: Approved with conditions

Review History

DateCertificateStageActionResultSourceDocs
2018-09-17 26754 Preliminary agenda_pdf Minutes
2018-09-17 Approved with conditions annual_report_api Minutes
2018-09-17 26754 Preliminary Calendared for Consent monthly_review_api Minutes
2019-09-16 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Rehabilitation of a sanitation garage and adjacent site work, Districts 11 and 1… Final 2019-11-18 2019-11-18
Subscribe to Updates Back to Projects