Installation of signage and doors (McDonald’s), 395 Flatbush Avenue Extension between Fulton Street and Dekalb Avenue, Brooklyn

Brooklyn · HPD · Signage · Final · Commented

Construction
Installation of specific elements
Public/Private
Private
First Seen
2018-07-09
Last Seen
2018-07-09

Stage Progression

Conceptual
Preliminary
2018-08-13
Final
2018-08-13
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2018-07-09 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Installation of signage and doors (McDonald’s), 395 Flatbush Avenue Extension be… Preliminary and Final 2018-08-13 2020-03-30