Construction of the Edenwald YMCA facility and adjacent site work, including a guard booth, athletic courts, and adjacent site work at the Christopher School Facility, 1250 East 229th Street at Schieffelin Place, Bronx
Bronx · EDC · Architecture · Approved with conditions
- City Council
- 12
- Community Board
- 12
- Construction
- Construction
- Public/Private
- Private
- Review Cycles
- 3
- First Seen
- 2018-03-12
- Last Seen
- 2018-03-12
Stage Progression
Conceptual
—
Preliminary
2018-03-12
Final
—
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2018-01-17 | Commented | annual_report_api | Minutes | |||
| 2018-02-12 | Commented | annual_report_api | Minutes | |||
| 2018-03-12 | 26528 | Preliminary | agenda_pdf | Minutes | ||
| 2018-03-12 | Approved with conditions | annual_report_api | Minutes | |||
| 2018-03-12 | 26528 | Preliminary | Calendared for Consent | monthly_review_api | Minutes |