Construction of an ADA ramp and adjacent site work, West 79th Street Rotunda, Riverside Park, West Terminus of 79th Street between Henry Hudson Parkway and the Hudson River, Manhattan
Manhattan · DOT · Landscape architecture · Final · Approved
- City Council
- 6
- Community Board
- 7
- Construction
- Construction
- Public/Private
- Public
- Review Cycles
- 2
- First Seen
- 2020-01-21
- Last Seen
- 2020-01-21
Stage Progression
Conceptual
—
Preliminary
2020-01-21
Final
2023-06-20
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2017-12-11 | Commented | annual_report_api | Minutes | |||
| 2018-09-17 | Commented | annual_report_api | Minutes | |||
| 2020-01-20 | Approved with conditions | annual_report_api | ||||
| 2020-01-21 | 27333 | Preliminary and Final | agenda_pdf | Minutes | ||
| 2020-01-21 | 27333 | Preliminary and Final | Calendared for Consent | monthly_review_api | Minutes |
Related Projects
Same project, different review stage (1)
| Title | Stage | First Seen | Last Seen |
|---|---|---|---|
| Construction of an ADA ramp and adjacent site work, West 79th Street Rotunda, Ri… | Amended Final | 2023-06-20 | 2023-06-20 |
Modifications (1)
| Title | Stage | First Seen | Result |
|---|---|---|---|
| Minor modifications to the construction of an ADA ramp and adjacent site work, W… | Amended Final | 2024-03-18 | Approved |