Installation of two prefabricated additions and adjacent site work, Horizon Juvenile Center, 560 Brook Avenue, Bronx

Bronx · DDC · Architecture · Final · Commented

Construction
Installation of specific elements
Public/Private
Public
First Seen
2017-11-13
Last Seen
2017-11-13

Stage Progression

Conceptual
Preliminary
2017-12-11
Final
2017-12-11
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2017-11-13 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Installation of two prefabricated additions and adjacent site work, Horizon Juve… 2017-12-11 2022-06-13
Other projects at this site (1)
TitleStageAgencyFirst Seen
Installation of interim trailers, Horizon Juvenile Center, 560 Brook Avenue, Bro… Preliminary and Final DDC 2018-05-14