Installation of a rooftop platform and stair, Queens Central Repair Shop, 52-35 58th Street, Woodside, Queens

Queens · DSNY · Building systems & Modifications · Final · Commented

City Council
30
Community Board
2
Construction
Installation of specific elements
Public/Private
Public
Review Cycles
1
First Seen
2017-08-14
Last Seen
2019-07-15

Stage Progression

Conceptual
Preliminary
2017-08-14
Final
2017-08-14
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2017-08-14 26304 Preliminary and Final agenda_pdf Minutes
2017-08-14 Approved annual_report_api Minutes
2019-07-15 Commented annual_report_api Minutes

Related Projects

Other projects at this site (1)
TitleStageAgencyFirst Seen
Construction of a substation and inverter and adjacent site work, Queens Central… DSNY 2018-11-14