Reconstruction of a plaza and adjacent site work, Queens Borough Hall, 120-55 Queens Boulevard, Kew Gardens, Queens

Queens · DDC · Building systems & Modifications · Final · Approved

City Council
29
Community Board
9
Construction
Reconstruction
Public/Private
Public
Review Cycles
1
First Seen
2017-05-22
Last Seen
2017-06-19

Stage Progression

Conceptual
Preliminary
2017-06-19
Final
2019-01-22
Preliminary → Final: 582 days

Review History

DateCertificateStageActionResultSourceDocs
2017-05-22 Found incomplete annual_report_api Minutes
2017-06-19 26187 Preliminary agenda_pdf Minutes
2017-06-19 Approved annual_report_api Minutes

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Reconstruction of a plaza and adjacent site work, Queens Borough Hall, 120-55 Qu… Final 2019-01-22 2019-01-22
Other projects at this site (4)
TitleStageAgencyFirst Seen
Installation of signage (One Claire Shulman Way), Queens Borough Hall, 120-55 Qu… Preliminary and Final DCAS 2021-03-22
Installation of HVAC equipment, Queens Borough Hall, 120-55 Queens Boulevard, Ke… Preliminary and Final DDC 2024-04-29
Installation of rooftop HVAC equipment, Queens Borough Hall, 120-55 Queens Boule… Preliminary and Final DCAS 2025-01-08
Minor modifications to the installation of rooftop HVAC equipment, Queens Boroug… Amended Final DCAS 2025-04-07