Construction of Biogas Conditioning System and Adjacent Site Work, Newtown Creek Wastewater Treatment Plant, 327 Greenpoint Ave, Brooklyn

Brooklyn · DEP · Architecture · Found incomplete

Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2017-04-24
Last Seen
2017-08-14

Stage Progression

Conceptual
Preliminary
Final
Result: Found incomplete

Review History

DateCertificateStageActionResultSourceDocs
2017-04-24 Approved annual_report_api Minutes
2017-08-14 Found incomplete annual_report_api Minutes

Related Projects

Other projects at this site (1)
TitleStageAgencyFirst Seen
Construction of Biogas Conditioning System and adjacent site work, Newtown Creek… DEP 2017-09-18
Subscribe to Updates Back to Projects