Construction of a concrete facility (Ferrara Brothers), 730 3rd Avenue between 24th Street, 25th Street, and the Gowanus Canal, Brooklyn

Brooklyn · EDC · Architecture · Final · Commented

City Council
38
Community Board
7
Construction
Construction
Public/Private
Private
Review Cycles
1
First Seen
2017-04-24
Last Seen
2017-12-11

Stage Progression

Conceptual
Preliminary
Final
2017-04-24
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2017-04-24 26128 Final agenda_pdf Minutes
2017-04-24 Approved annual_report_api Minutes
2017-12-11 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Construction of a concrete facility (Ferrara Brothers), 730 3rd Avenue between 2… 2017-01-18 2017-03-13
Other projects at this site (1)
TitleStageAgencyFirst Seen
Construction of a concrete facility (Ferrara Brothers), 730 3rd Avenue between 2…