Installation of anodes and barge bumpers, Vernon C. Bain Center, 1 Halleck Street, Bronx

Bronx · DOC · Building systems & Modifications · Final · Approved

City Council
17
Community Board
2
Construction
Installation of specific elements
Public/Private
Public
Review Cycles
1
First Seen
2017-03-13
Last Seen
2017-03-13

Stage Progression

Conceptual
Preliminary
2017-03-13
Final
2017-03-13

Review History

DateCertificateStageActionResultSourceDocs
2017-03-13 26069 Preliminary and Final agenda_pdf Minutes
2017-03-13 Approved annual_report_api Minutes

Related Projects

Other projects at this site (2)
TitleStageAgencyFirst Seen
Installation of a louver and exhaust fan, Vernon C. Bain Center, 1 Halleck Stree…
Reconstruction of a utility building and security booth, Vernon C. Bain Center, … Preliminary and Final DOC 2021-04-26