Construction of a utility building and installation of diesel fuel storage tanks, Pier C, Brooklyn Navy Yard Industrial Park, 63 Flushing Avenue, Brooklyn

Brooklyn · EDC · Architecture · Final · Approved

City Council
33
Community Board
2
Construction
Construction
Public/Private
Private
Review Cycles
1
First Seen
2017-03-13
Last Seen
2017-03-13

Stage Progression

Conceptual
Preliminary
2016-12-12
Final
2017-03-13
Preliminary → Final: 91 days

Review History

DateCertificateStageActionResultSourceDocs
2017-03-13 26086 Final agenda_pdf Minutes
2017-03-13 Approved annual_report_api Minutes

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Construction of a utility building and installation of diesel fuel storage tanks…
Construction of a utility building and installation of diesel fuel storage tanks… 2017-01-18 2017-02-13
Other projects at this site (2)
TitleStageAgencyFirst Seen
Construction of a warehouse building and locker room building, Pier C, Brooklyn … EDC 2017-09-18
Installation of wave attenuation piles and barges, Pier C, Brooklyn Navy Yard In… Preliminary and Final EDC 2023-11-13
Subscribe to Updates Back to Projects