Reconstruction of a playground and adjacent site work, Asser Levy Park, Sea Breeze Avenue, West Fifth Street, and Surf Avenue, Brooklyn
Brooklyn · DPR · Landscape architecture · Final · Commented
- Construction
- Reconstruction
- Public/Private
- Public
- First Seen
- 2017-12-11
- Last Seen
- 2017-12-11
Stage Progression
Conceptual
—
Preliminary
—
Final
2016-12-12
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2017-12-11 | Commented | annual_report_api | Minutes |
Related Projects
Same project, different review stage (1)
| Title | Stage | First Seen | Last Seen |
|---|---|---|---|
| Reconstruction of a playground and adjacent site work, Asser Levy Park, Sea Bree… |
Other projects at this site (4)
| Title | Stage | Agency | First Seen |
|---|---|---|---|
| Reconstruction of a playground and adjacent site work, Asser Levy Park, Sea Bree… | |||
| Construction of an adult fitness area, Asser Levy Park, Sea Breeze Avenue, West … | Preliminary | DPR | 2018-04-16 |
| Construction of an adult fitness area, Asser Levy Park, Sea Breeze Avenue, West … | Final | DPR | 2018-09-17 |