Installation of rooftop equipment atop the Great Hall, New York Hall of Science, 47-01 111th Street, Queens

Queens · DDC · Building systems & Modifications · Final · Commented

Construction
Installation of specific elements
Public/Private
Public
First Seen
2024-12-16
Last Seen
2024-12-16

Stage Progression

Conceptual
Preliminary
2016-08-22
Final
2016-08-22
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2024-12-16 Commented annual_report_api Minutes

Meeting Videos

Public Design Commission Meeting, Monday, December 16, 2024 (2024-12-16)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Installation of rooftop equipment atop the Great Hall, New York Hall of Science,…
Other projects at this site (4)
TitleStageAgencyFirst Seen
Installation of bird-proofing material, New York Hall of Science, 47-01 111th St…
Installation of bird-proofing material, New York Hall of Science, 47-01 111th St…
Reconstruction of the terrace atop the Central Pavilion and the Great Hall entry…
Reconstruction of the Great Hall entrance and the terrace atop the Central Pavil…
Subscribe to Updates Back to Projects