Installation of Para Roberto by Melissa Calderon, Roberto Clemente Plaza, Third Avenue, East 147th Street, East 149th Street, and Willis Avenue, Bronx

Bronx · DDC · Artwork · Final · Approved

Construction
Installation of specific elements
Public/Private
Public
First Seen
2018-04-16
Last Seen
2018-04-16

Stage Progression

Conceptual
2016-10-17
Preliminary
2018-08-13
Final
2019-11-18
Conceptual → Preliminary: 665 days
Preliminary → Final: 462 days

Review History

DateCertificateStageActionResultSourceDocs
2018-04-16 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (3)
TitleStageFirst SeenLast Seen
Installation of Para Roberto by Melissa Calderon, Roberto Clemente Plaza, Third …
Installation of Para Roberto by Melissa Calderon, Roberto Clemente Plaza, Third … Preliminary 2018-08-13 2019-06-17
Installation of Para Roberto by Melissa Calderon, Roberto Clemente Plaza, Third … Final 2019-11-18 2019-11-18