Reconstruction of Newtown Barge Park as part of the Greenpoint and Williamsburg waterfront master plan, Commercial Street, Dupont Street and the East River, Brooklyn

Brooklyn · EDC · Landscape architecture · Final · Commented

Construction
Reconstruction
Public/Private
Public
First Seen
2019-10-21
Last Seen
2019-10-21

Stage Progression

Conceptual
Preliminary
2015-05-11
Final
2015-12-07
Preliminary → Final: 210 days
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2019-10-21 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Reconstruction of Newtown Barge Park as part of the Greenpoint and Williamsburg …
Reconstruction of Newtown Barge Park as part of the Greenpoint and Williamsburg …
Subscribe to Updates Back to Projects