Reconstruction of Playground 52, Phase II, Avenue St. John, Beck Street and Kelly Street, Bronx
Bronx · DPR · Landscape architecture · Commented
- Construction
- Reconstruction
- Public/Private
- Public
- First Seen
- 2018-07-09
- Last Seen
- 2018-07-09
Stage Progression
Conceptual
—
Preliminary
—
Final
—
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2018-07-09 | Commented | annual_report_api | Minutes |