| Conservation and relocation of the Washington Kill Von Kull Monument (1932), Faber Park, Richmond Terrace between Sharpe Avenue and Faber Street, Staten Island |
Staten Island |
DPR |
Final |
|
Consent Items |
Agenda
Minutes
|
| Construction of a flood wall and resiliency infrastructure, including a portion of the Brooklyn Waterfront Greenway (Red Hook Coastal Resiliency), from Summit Street at Hamilton Avenue to Ferris Street at Coffey Street, and to Halleck Street at Columbia Street, Brooklyn |
Brooklyn |
DDC |
Preliminary |
|
Consent Items |
Agenda
Minutes
|
| Construction of a plaza, Osborn Street south of Belmont Avenue, Brooklyn |
Brooklyn |
DDC |
Final |
|
Consent Items |
Agenda
Minutes
|
| Construction of flood protection measures and moveable planters as part of the South Battery Park City Resiliency master plan, 1st Place between Battery Place and the Battery Park City Esplanade, Manhattan |
Manhattan |
DOT |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Design of a prototypical louver at the transoms of Building 303 (formerly Building 399), Sands Street between Navy Street, Third Street, and Chauncey Avenue, Brooklyn Navy Yard Industrial Park, Brooklyn |
Brooklyn |
BNYDC |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Installation of a conduit support system, Final Settling Tanks, Red Hook Wastewater Resource Recovery Facility, West Street between East Way and Little Street, Brooklyn Navy Yard Industrial Park, Brooklyn |
Brooklyn |
DEP |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Installation of a fenced-in area with stairs and a wheelchair lift, 202 St. Nicholas Avenue, Manhattan |
Manhattan |
DOT |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Installation of a temporary mural, After the Fire by Nanibah Chacon, Tatyana Fazlalizadeh, and Layqa Nuna Yawar, MoMA PS1, 46-01 21st Street, Long Island City, Queens |
Queens |
DCLA |
Final |
|
Consent Items |
Agenda
Minutes
|
| Installation of decorative tree guards, West Side Federation for Senior and Supportive Housing, 141-145 West 108th Street, Manhattan |
Manhattan |
DPR |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Installation of rooftop HVAC equipment, skylights and doors, and adjacent site work, Headworks Building, Tallman Island Wastewater Resource Recovery Facility, 127th Street and Powell's Cove Boulevard, College Point, Queens |
Queens |
DEP |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Installation of rooftop mechanical equipment, Rescue 1, 530 West 43rd Street, Manhattan |
Manhattan |
FDNY |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Installation of rooftop mechanical units, 100th Police Precinct, 92-24 Rockaway Beach Boulevard, Rockaway Beach, Queens |
Queens |
NYPD |
Final |
|
Consent Items |
Agenda
Minutes
|
| Installation of security bollards, Phase III, Moynihan Station (formerly Farley Post Office), 421 Eighth Avenue, Ninth Avenue between West 31st Street and West 33rd Street, Manhattan |
Manhattan |
DOT |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Installation of signage, including digital signage, Citi Field, 120-01 Roosevelt Avenue, Flushing Meadows Corona Park, Corona, Queens |
Queens |
DPR |
Preliminary |
|
Consent Items |
Agenda
Minutes
|
| Installation of signage (Primark), CityPoint, 1 Dekalb Avenue (445 Albee Square West), Fleet Street, Albee Square, and Albee Square West, Brooklyn |
Brooklyn |
EDC |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Installation of signage (Stop & Shop), 625 Atlantic Avenue, Brooklyn |
Brooklyn |
EDC |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Reconstruction of a landscape, North Meadow Recreation Center, West Drive and 97th Street Transverse Road, Central Park, Manhattan |
Manhattan |
DPR |
Final |
|
Consent Items |
Agenda
Minutes
|
| Reconstruction of an operations facility, relocation of a playground, and adjacent site work, Coney Island Beach Operations Headquarters, Poseidon Playground, 3026 West 25th Street, West 27th Street, Surf Avenue, West 25th Street, and the Riegelmann Boardwalk, Brooklyn |
Brooklyn |
DDC |
Preliminary |
|
Consent Items |
Agenda
Minutes
|
| Reconstruction of Queens Boulevard from 73rd Street to Eliot Avenue, as Phase II of the reconstruction of Queens Boulevard from Roosevelt Avenue to Union Turnpike, Elmhurst and Rego Park, Queens |
Queens |
DDC |
Preliminary |
|
Consent Items |
Agenda
Minutes
|
| Reconstruction of the esplanade and adjacent site work (Lower Manhattan Coastal Resiliency), The Battery, Battery Place, State Street, Peter Minuit Plaza, and Upper New York Bay, Manhattan |
Manhattan |
EDC |
Final |
|
Consent Items |
Agenda
Minutes
|
| Reconstruction of the playground, Hamilton Fish Park, Pitt Street, East Houston Street, and Sheriff Street, Manhattan |
Manhattan |
DPR |
Final |
|
Consent Items |
Agenda
Minutes
|
| Rehabilitation of a comfort station, Little Flower Playground, Madison Street, Jefferson Street, and Cherry Street, Manhattan |
Manhattan |
DPR |
Preliminary |
|
Consent Items |
Agenda
Minutes
|
| Rehabilitation of a comfort station, P.S. 155 Playground, First Avenue, East 117th Street, Second Avenue, and East 118th Street, Manhattan |
Manhattan |
DPR |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Rehabilitation of a pool facility and adjacent site work, Haffen Park, Burke Avenue and Ely Avenue, Bronx |
Bronx |
DPR |
Final |
|
Consent Items |
Agenda
Minutes
|
| Rehabilitation of rooftop bulkheads, Building 3, South Street between Seventh Avenue and Eighth Avenue, Brooklyn Navy Yard Industrial Park, Brooklyn |
Brooklyn |
BNYDC |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Rehabilitation of the east façade, Bellevue Men's Shelter, 400 East 30th Street, Manhattan |
Manhattan |
DDC |
Preliminary and Final |
|
Consent Items |
Agenda
Minutes
|
| Rehabilitation of the Hudson River Drainage Chamber and adjacent site work, Breakneck Point, Town of Fishkill, Dutchess County |
Upstate |
DEP |
Preliminary |
|
Consent Items |
Agenda
Minutes
|
| Design of prototypical public communications structures (Link5G) in Residence Zoning and Historic Districts, Phase I pilot, for installation citywide |
Citywide |
OTI |
Preliminary and Final |
|
Public Hearing |
Agenda
Minutes
|
| Construction of an amphitheater as part of East Side Coastal Resiliency (ESCR), Jackson Street, Cherry Street, and the FDR Drive, East River Park, Manhattan |
Manhattan |
DDC |
Preliminary |
|
Public Hearing |
Agenda
Minutes
|
| Conservation and relocation of the Washington Kill Von Kull Monument (1932), Faber Park, Richmond Terrace between Sharpe Avenue and Faber Street, Staten Island |
Staten Island |
DPR |
Final |
|
|
Agenda
Minutes
|
| Conservation and relocation of the Washington Kill Von Kull Monument (1932), Faber Park, Richmond Terrace between Sharpe Avenue and Faber Street, Staten Island |
Staten Island |
DPR |
|
Approved |
|
Agenda
Minutes
|
| Conservation of the Kimlau War Memorial (1962) by Poy G. Lee, Park Row and Chatham Square, Kimlau Square, Manhattan |
Manhattan |
DPR |
|
Withdrawn |
|
Agenda
Minutes
|
| Construction of ADA ramps and restoration of the Conservatory Garden, Phase II, Central Park, Fifth Avenue at East 105th Street, Manhattan |
Manhattan |
DPR |
|
Commented |
|
Agenda
Minutes
|
| Construction of a field operations building, adaptive reuse of the former Fluoride Building, and adjacent site work, 601 Midland Avenue, Yonkers |
Upstate |
DEP |
|
Commented |
|
Agenda
Minutes
|
| Construction of a flood wall and resiliency infrastructure, including a portion of the Brooklyn Waterfront Greenway (Red Hook Coastal Resiliency), from Summit Street at Hamilton Avenue to Ferris Street at Coffey Street, and to Halleck Street at Columbia Street, Brooklyn |
Brooklyn |
DDC |
Preliminary |
|
|
Agenda
Minutes
|
| Construction of a flood wall and resiliency infrastructure, including a portion of the Brooklyn Waterfront Greenway (Red Hook Coastal Resiliency), from Summit Street at Hamilton Avenue to Ferris Street at Coffey Street, and to Halleck Street at Columbia Street, Brooklyn |
Brooklyn |
DDC |
|
Approved with conditions |
|
Agenda
Minutes
|
| Construction of an amphitheater as part of East Side Coastal Resiliency (ESCR), Jackson Street, Cherry Street, and the FDR Drive, East River Park, Manhattan |
Manhattan |
DDC |
|
Approved with conditions |
|
Agenda
Minutes
|
| Construction of an amphitheater as part of East Side Coastal Resiliency (ESCR), Jackson Street, Cherry Street, and the FDR Drive, East River Park, Manhattan |
Manhattan |
DDC |
Preliminary |
|
|
Agenda
Minutes
|
| Construction of an electrical building, relocation of West Lake Drive, and adjacent site work as part of the Kensico-Eastview Connection Project, 19 Westlake Drive, Mount Pleasant, Westchester County |
Upstate |
DEP |
|
Commented |
|
Agenda
Minutes
|
| Construction of an operations facility, Rockaway Operational Headquarters, 3-75 Beach 75th Street, Arverne, Queens |
Queens |
DDC |
|
Commented |
|
Agenda
Minutes
|
| Construction of a playground, plaza, and adjacent site work, Faber Park, Richmond Terrace between Sharpe Avenue and Faber Street, Staten Island |
Staten Island |
DPR |
|
Commented |
|
Agenda
Minutes
|
| Construction of a plaza, Osborn Street south of Belmont Avenue, Brooklyn |
Brooklyn |
DDC |
|
Approved |
|
Agenda
Minutes
|
| Construction of a plaza, Osborn Street south of Belmont Avenue, Brooklyn |
Brooklyn |
DDC |
Final |
|
|
Agenda
Minutes
|
| Construction of a public health laboratory, Harlem Hospital Center, Lenox Avenue, West 137th Street, Fifth Avenue, and West 136th Street, Manhattan |
Manhattan |
EDC |
|
Commented |
|
Agenda
Minutes
|
| Construction of a residential building, streetscape, and plazas, 126th Street and Roosevelt Avenue, Willets Point, Corona, Queens |
Queens |
EDC |
|
Commented |
|
Agenda
Minutes
|
| Construction of flood protection measures and moveable planters as part of the South Battery Park City Resiliency master plan, 1st Place between Battery Place and the Battery Park City Esplanade, Manhattan |
Manhattan |
DOT |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Construction of flood protection measures and moveable planters as part of the South Battery Park City Resiliency master plan, 1st Place between Battery Place and the Battery Park City Esplanade, Manhattan |
Manhattan |
DOT |
|
Approved |
|
Agenda
Minutes
|
| Design of a prototypical louver at the transoms of Building 303 (formerly Building 399), Sands Street between Navy Street, Third Street, and Chauncey Avenue, Brooklyn Navy Yard Industrial Park, Brooklyn |
Brooklyn |
BNYDC |
|
Approved |
|
Agenda
Minutes
|
| Design of a prototypical louver at the transoms of Building 303 (formerly Building 399), Sands Street between Navy Street, Third Street, and Chauncey Avenue, Brooklyn Navy Yard Industrial Park, Brooklyn |
Brooklyn |
BNYDC |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Design of a wayfinding and environmental graphics system, Brooklyn Navy Yard Industrial Park, Brooklyn |
Brooklyn |
BNYDC |
|
Withdrawn |
|
Agenda
Minutes
|
| Design of prototypical public communications structures (Link5G) in Residence Zoning and Historic Districts, Phase I pilot, for installation citywide |
Citywide |
OTI |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Design of prototypical public communications structures (Link5G) in Residence Zoning and Historic Districts, Phase I pilot, for installation citywide |
Citywide |
OTI |
|
Approved with conditions |
|
Agenda
Minutes
|
| Installation of a conduit support system, Final Settling Tanks, Red Hook Wastewater Resource Recovery Facility, West Street between East Way and Little Street, Brooklyn Navy Yard Industrial Park, Brooklyn |
Brooklyn |
DEP |
|
Approved |
|
Agenda
Minutes
|
| Installation of a conduit support system, Final Settling Tanks, Red Hook Wastewater Resource Recovery Facility, West Street between East Way and Little Street, Brooklyn Navy Yard Industrial Park, Brooklyn |
Brooklyn |
DEP |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Installation of a fenced-in area with stairs and a wheelchair lift, 202 St. Nicholas Avenue, Manhattan |
Manhattan |
DOT |
|
Approved |
|
Agenda
Minutes
|
| Installation of a fenced-in area with stairs and a wheelchair lift, 202 St. Nicholas Avenue, Manhattan |
Manhattan |
DOT |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Installation of a modular comfort station and adjacent site work, Discovery Playground, Fort Washington Park, Henry Hudson Parkway near West 163rd Street, Manhattan |
Manhattan |
DPR |
|
Commented |
|
Agenda
Minutes
|
| Installation of a permanent perimeter fence, Newtown Creek Wastewater Pollution Control Plant, Provost Street, Greenpoint Avenue, and Kingsland Avenue, Brooklyn |
Brooklyn |
DEP |
|
Commented |
|
Agenda
Minutes
|
| Installation of a storefront system and louvers, 430 East 29th Street (East Tower), East River Science Park (Alexandria Center for Life Science), Manhattan |
Manhattan |
EDC |
|
Commented |
|
Agenda
Minutes
|
| Installation of a temporary mural, After the Fire by Nanibah Chacon, Tatyana Fazlalizadeh, and Layqa Nuna Yawar, MoMA PS1, 46-01 21st Street, Long Island City, Queens |
Queens |
DCLA |
|
Approved |
|
Agenda
Minutes
|
| Installation of a temporary mural, After the Fire by Nanibah Chacon, Tatyana Fazlalizadeh, and Layqa Nuna Yawar, MoMA PS1, 46-01 21st Street, Long Island City, Queens |
Queens |
DCLA |
Final |
|
|
Agenda
Minutes
|
| Installation of decorative tree guards, West Side Federation for Senior and Supportive Housing, 141-145 West 108th Street, Manhattan |
Manhattan |
DPR |
|
Approved |
|
Agenda
Minutes
|
| Installation of decorative tree guards, West Side Federation for Senior and Supportive Housing, 141-145 West 108th Street, Manhattan |
Manhattan |
DPR |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Installation of Resonances by Christopher Myers, Brownsville Library, 61 Glenmore Avenue, Brooklyn |
Brooklyn |
DCLA% |
|
Commented |
|
Agenda
Minutes
|
| Installation of rooftop HVAC equipment, skylights and doors, and adjacent site work, Headworks Building, Tallman Island Wastewater Resource Recovery Facility, 127th Street and Powell's Cove Boulevard, College Point, Queens |
Queens |
DEP |
|
Approved |
|
Agenda
Minutes
|
| Installation of rooftop HVAC equipment, skylights and doors, and adjacent site work, Headworks Building, Tallman Island Wastewater Resource Recovery Facility, 127th Street and Powell's Cove Boulevard, College Point, Queens |
Queens |
DEP |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Installation of rooftop mechanical equipment, Rescue 1, 530 West 43rd Street, Manhattan |
Manhattan |
FDNY |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Installation of rooftop mechanical equipment, Rescue 1, 530 West 43rd Street, Manhattan |
Manhattan |
FDNY |
|
Approved |
|
Agenda
Minutes
|
| Installation of rooftop mechanical units, 100th Police Precinct, 92-24 Rockaway Beach Boulevard, Rockaway Beach, Queens |
Queens |
NYPD |
Final |
|
|
Agenda
Minutes
|
| Installation of rooftop mechanical units, 100th Police Precinct, 92-24 Rockaway Beach Boulevard, Rockaway Beach, Queens |
Queens |
NYPD |
|
Approved |
|
Agenda
Minutes
|
| Installation of rooftop photovoltaic panels, 300 West 206th Street, Manhattan |
Manhattan |
DOT |
|
Commented |
|
Agenda
Minutes
|
| Installation of security bollards, Phase III, Moynihan Station (formerly Farley Post Office), 421 Eighth Avenue, Ninth Avenue between West 31st Street and West 33rd Street, Manhattan |
Manhattan |
DOT |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Installation of security bollards, Phase III, Moynihan Station (formerly Farley Post Office), 421 Eighth Avenue, Ninth Avenue between West 31st Street and West 33rd Street, Manhattan |
Manhattan |
DOT |
|
Approved |
|
Agenda
Minutes
|
| Installation of signage as part of a park-wide signage system, Pier 97, between West 57th Street and West 59th Street, Manhattan |
Manhattan |
DPR |
|
Commented |
|
Agenda
Minutes
|
| Installation of signage, including digital signage, Citi Field, 120-01 Roosevelt Avenue, Flushing Meadows Corona Park, Corona, Queens |
Queens |
DPR |
Preliminary |
|
|
Agenda
Minutes
|
| Installation of signage, including digital signage, Citi Field, 120-01 Roosevelt Avenue, Flushing Meadows Corona Park, Corona, Queens |
Queens |
DPR |
|
Approved |
|
Agenda
Minutes
|
| Installation of signage (New York Blood Center), 30 Flatbush Avenue, Brooklyn |
Brooklyn |
HPD |
|
Commented |
|
Agenda
Minutes
|
| Installation of signage (Primark), CityPoint, 1 Dekalb Avenue (445 Albee Square West), Fleet Street, Albee Square, and Albee Square West, Brooklyn |
Brooklyn |
EDC |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Installation of signage (Primark), CityPoint, 1 Dekalb Avenue (445 Albee Square West), Fleet Street, Albee Square, and Albee Square West, Brooklyn |
Brooklyn |
EDC |
|
Approved |
|
Agenda
Minutes
|
| Installation of signage (Stop & Shop), 625 Atlantic Avenue, Brooklyn |
Brooklyn |
EDC |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Installation of signage (Stop & Shop), 625 Atlantic Avenue, Brooklyn |
Brooklyn |
EDC |
|
Approved |
|
Agenda
Minutes
|
| Installation of wayfinding signage, MetroTech Center (Brooklyn Commons), Myrtle Avenue Promenade and MetroTech Commons between Jay Street and Flatbush Avenue, Brooklyn |
Brooklyn |
EDC |
|
Commented |
|
Agenda
Minutes
|
| Reconstruction of a landscape, North Meadow Recreation Center, West Drive and 97th Street Transverse Road, Central Park, Manhattan |
Manhattan |
DPR |
Final |
|
|
Agenda
Minutes
|
| Reconstruction of a landscape, North Meadow Recreation Center, West Drive and 97th Street Transverse Road, Central Park, Manhattan |
Manhattan |
DPR |
|
Approved |
|
Agenda
Minutes
|
| Reconstruction of an operations facility, relocation of a playground, and adjacent site work, Coney Island Beach Operations Headquarters, Poseidon Playground, 3026 West 25th Street, West 27th Street, Surf Avenue, West 25th Street, and the Riegelmann Boardwalk, Brooklyn |
Brooklyn |
DDC |
|
Approved |
|
Agenda
Minutes
|
| Reconstruction of an operations facility, relocation of a playground, and adjacent site work, Coney Island Beach Operations Headquarters, Poseidon Playground, 3026 West 25th Street, West 27th Street, Surf Avenue, West 25th Street, and the Riegelmann Boardwalk, Brooklyn |
Brooklyn |
DDC |
Preliminary |
|
|
Agenda
Minutes
|
| Reconstruction of a park, Elizabeth H. Berger Plaza, Greenwich Street, Edgar Street, Trinity Place, and Morris Street, Manhattan |
Manhattan |
DPR |
|
Commented |
|
Agenda
Minutes
|
| Reconstruction of a storefront and installation of a rooftop mechanical enclosure, 3rd Street Women's Shelter, Manhattan |
Manhattan |
DDC |
|
Commented |
|
Agenda
Minutes
|
| Reconstruction of a swimming pool and skating rink (Lasker Rink) and adjacent site work, between East Drive and the Harlem Meer, Central Park, Manhattan |
Manhattan |
DPR |
|
Commented |
|
Agenda
Minutes
|
| Reconstruction of Gate Houses No. 2 and 3 and rehabilitation of Gate Houses No. 5 and 7, Jerome Park Reservoir, Sedgwick Avenue, Goulden Avenue and Reservoir Avenue, Bronx |
Bronx |
DEP |
|
Commented |
|
Agenda
Minutes
|
| Reconstruction of Lawrence Playground, College Point Boulevard, Botanical Garden Bridge, and the Van Wyck Expressway, Queens |
Queens |
DPR |
|
Commented |
|
Agenda
Minutes
|
| Reconstruction of Pershing Square East Plaza, Park Avenue between East 41st Street and East 42nd Street, Manhattan |
Manhattan |
DDC |
|
Commented |
|
Agenda
Minutes
|
| Reconstruction of Pontiac Playground, adjacent to P.S. 5, East 150th Street between Jackson Avenue and Concord Avenue, Bronx |
Bronx |
DPR |
|
Commented |
|
Agenda
Minutes
|
| Reconstruction of Queens Boulevard from 73rd Street to Eliot Avenue, as Phase II of the reconstruction of Queens Boulevard from Roosevelt Avenue to Union Turnpike, Elmhurst and Rego Park, Queens |
Queens |
DDC |
|
Approved |
|
Agenda
Minutes
|
| Reconstruction of Queens Boulevard from 73rd Street to Eliot Avenue, as Phase II of the reconstruction of Queens Boulevard from Roosevelt Avenue to Union Turnpike, Elmhurst and Rego Park, Queens |
Queens |
DDC |
Preliminary |
|
|
Agenda
Minutes
|
| Reconstruction of the coastline (East Side Coastal Resiliency) and East River Park, including the construction of three bridges, a comfort station, two recreation centers, and two gate houses, East River between Montgomery Street and East 25th Street, Manhattan |
Manhattan |
DDC |
|
Commented |
|
Agenda
Minutes
|
| Reconstruction of the Cumberland Street Gate and Clinton Avenue Gate, and adjacent site work, Flushing Avenue at Cumberland Street and Sixth Street, and at Clinton Avenue and Tenth Avenue, Brooklyn Navy Yard Industrial Park, Brooklyn |
Brooklyn |
BNYDC |
|
Withdrawn |
|
Agenda
Minutes
|
| Reconstruction of the esplanade and adjacent site work (Lower Manhattan Coastal Resiliency), The Battery, Battery Place, State Street, Peter Minuit Plaza, and Upper New York Bay, Manhattan |
Manhattan |
EDC |
Final |
|
|
Agenda
Minutes
|
| Reconstruction of the esplanade and adjacent site work (Lower Manhattan Coastal Resiliency), The Battery, Battery Place, State Street, Peter Minuit Plaza, and Upper New York Bay, Manhattan |
Manhattan |
EDC |
|
Approved with conditions |
|
Agenda
Minutes
|
| Reconstruction of the playground, Hamilton Fish Park, Pitt Street, East Houston Street, and Sheriff Street, Manhattan |
Manhattan |
DPR |
Final |
|
|
Agenda
Minutes
|
| Reconstruction of the playground, Hamilton Fish Park, Pitt Street, East Houston Street, and Sheriff Street, Manhattan |
Manhattan |
DPR |
|
Approved |
|
Agenda
Minutes
|
| Reconstruction of the plaza and pavilion, Poe Park, East 192nd Street and the Grand Concourse, Bronx |
Bronx |
DPR |
|
Commented |
|
Agenda
Minutes
|
| Reconstruction of the roof, Ozone Park Branch Library, 92-24 Rockaway Boulevard, Ozone Park, Queens |
Queens |
DDC |
|
Commented |
|
Agenda
Minutes
|
| Rehabilitation of a comfort station, Grove Hill Playground, adjacent to P.S. 157, East 158th Street between Eagle Avenue and Cauldwell Avenue, Bronx |
Bronx |
DPR |
|
Commented |
|
Agenda
Minutes
|
| Rehabilitation of a comfort station, Little Flower Playground, Madison Street, Jefferson Street, and Cherry Street, Manhattan |
Manhattan |
DPR |
Preliminary |
|
|
Agenda
Minutes
|
| Rehabilitation of a comfort station, Little Flower Playground, Madison Street, Jefferson Street, and Cherry Street, Manhattan |
Manhattan |
DPR |
|
Approved |
|
Agenda
Minutes
|
| Rehabilitation of a comfort station, P.S. 155 Playground, First Avenue, East 117th Street, Second Avenue, and East 118th Street, Manhattan |
Manhattan |
DPR |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Rehabilitation of a comfort station, P.S. 155 Playground, First Avenue, East 117th Street, Second Avenue, and East 118th Street, Manhattan |
Manhattan |
DPR |
|
Approved |
|
Agenda
Minutes
|
| Rehabilitation of a pool facility and adjacent site work, Haffen Park, Burke Avenue and Ely Avenue, Bronx |
Bronx |
DPR |
|
Approved |
|
Agenda
Minutes
|
| Rehabilitation of a pool facility and adjacent site work, Haffen Park, Burke Avenue and Ely Avenue, Bronx |
Bronx |
DPR |
Final |
|
|
Agenda
Minutes
|
| Rehabilitation of rooftop bulkheads, Building 3, South Street between Seventh Avenue and Eighth Avenue, Brooklyn Navy Yard Industrial Park, Brooklyn |
Brooklyn |
BNYDC |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Rehabilitation of rooftop bulkheads, Building 3, South Street between Seventh Avenue and Eighth Avenue, Brooklyn Navy Yard Industrial Park, Brooklyn |
Brooklyn |
BNYDC |
|
Approved |
|
Agenda
Minutes
|
| Rehabilitation of the east façade, Bellevue Men's Shelter, 400 East 30th Street, Manhattan |
Manhattan |
DDC |
|
Approved |
|
Agenda
Minutes
|
| Rehabilitation of the east façade, Bellevue Men's Shelter, 400 East 30th Street, Manhattan |
Manhattan |
DDC |
Preliminary and Final |
|
|
Agenda
Minutes
|
| Rehabilitation of the east facade, including the installation of signage, West Farms Branch Library, 2085 Honeywell Avenue, Bronx |
Bronx |
DDC |
|
Commented |
|
Agenda
Minutes
|
| Rehabilitation of the Hudson River Drainage Chamber and adjacent site work, Breakneck Point, Town of Fishkill, Dutchess County |
Upstate |
DEP |
|
Approved with conditions |
|
Agenda
Minutes
|
| Rehabilitation of the Hudson River Drainage Chamber and adjacent site work, Breakneck Point, Town of Fishkill, Dutchess County |
Upstate |
DEP |
Preliminary |
|
|
Agenda
Minutes
|