| Construction of a park, High Line elevated rail line, Phase II, West 20th Street to West 30th Street between Tenth Avenue and Eleventh Avenue, Manhattan |
|
|
Final |
|
Committee Meeting |
Agenda
|
| Construction of North Park, Phase I, Fresh Kills Park, Richmond Hill Road, Arthur Kill Road and Victory Boulevard, Staten Island |
|
|
Preliminary |
|
Committee Meeting |
Agenda
|
| Construction of a comfort station, Schmul Park as part of Phase I, Wild Avenue, Pearson Street and Melvin Avenue, Staten Island |
|
|
Preliminary |
|
Committee Meeting |
Agenda
|
| Reconstruction of an entrance, Central Park, 102nd Street and Fifth Avenue, Manhattan |
|
|
Preliminary |
|
Committee Meeting |
Agenda
|
| Construction of an environmental education center and rehabilitation of and addition to the current facility, including adjacent site work, New York Restoration Project’s Sherman Creek Campus, Sherman Creek Park, 10th Avenue, Harlem River Drive, Academy Street and Sherman Creek, Manhattan |
|
|
Preliminary |
|
Committee Meeting |
Agenda
|
| Construction of a park, Phase I, including an entry plaza and expansion of the parking lot, Midland Beach, Father Capodanno Boulevard between Slater Boulevard and Seaview Avenue, Staten Island |
|
|
Final |
|
Committee Meeting |
Agenda
|
| Construction of a tennis center, Randall’s Island, Manhattan |
|
|
Final |
|
Committee Meeting |
Agenda
|
| Reconstruction of the Columbus Avenue promenade, Lincoln Center for the Performing Arts, 70 Lincoln Center Plaza, Manhattan |
|
|
Preliminary and Final |
|
Committee Meeting |
Agenda
|
| Reconstruction of the track and field, Corporal Lawrence Thompson Park, Henderson Avenue, Broadway and Chapell Street, Staten Island |
|
|
Preliminary and Final |
|
Committee Meeting |
Agenda
|
| Rehabilitation of the Shaft 11A headhouse and adjacent site work, New Croton Aqueduct, White Plains Road, Greenburgh, Westchester County, New York |
|
|
Final |
|
Committee Meeting |
Agenda
|
| Rehabilitation of the Shaft 18 gatehouse and adjacent site work, New Croton Aqueduct, Yonkers Avenue, Yonkers, Westchester County, New York |
|
|
Final |
|
Committee Meeting |
Agenda
|
| Rehabilitation of the Shaft 23 headhouse and adjacent site work, New Croton Aqueduct, West Burnside Avenue, University Heights, Bronx |
|
|
Final |
|
Committee Meeting |
Agenda
|
| Rehabilitation of the Shaft 25 headhouse and adjacent site work, New Croton Aqueduct, Highbridge Park, Manhattan |
|
|
Final |
|
Committee Meeting |
Agenda
|
| Rehabilitation of the Shaft 9 gatehouse and adjacent site work, New Croton Aqueduct, Sleepy Hollow Road, Sleepy Hollow, Westchester County, New York |
|
|
Final |
|
Committee Meeting |
Agenda
|
| Installation of 16 signs as part of a campus-wide wayfinding signage program, New York Presbyterian Hospital and Columbia University Medical Center, West 168th Street, St. Nicholas Avenue, West 165th Street and Riverside Drive, Manhattan |
|
|
Preliminary and Final |
|
Consent Items |
Agenda
|
| Installation of 22 M-poles, 86th Street between Fourth Avenue and Fort Hamilton Parkway, Brooklyn |
|
|
Preliminary and Final |
|
Consent Items |
Agenda
|
| Installation of a planted area, LaGuardia Center, 45th Street between Ditmars Boulevard and 23rd Avenue, Queens |
|
|
Preliminary and Final |
|
Consent Items |
Agenda
|
| Installation of four fenced-in planted areas, 15 Central Park West, Manhattan |
|
|
Preliminary and Final |
|
Consent Items |
Agenda
|
| Installation of streetscape improvements, including the reconstruction of Albee Square, Fulton Mall, Fulton Street from Adams Street to Flatbush Avenue, Brooklyn |
|
|
Final |
|
Consent Items |
Agenda
|
| Reconstruction of Engine Company 63/Ladder 39/Battalion 15, including the construction of an addition, 755 East 233rd Street, Bronx |
|
|
Preliminary |
|
Consent Items |
Agenda
|
| Reconstruction of the Arthur Avenue Retail Market, 2344 Arthur Avenue, Bronx |
|
|
Final |
|
Consent Items |
Agenda
|
| Reconstruction of the entrance, Queensboro Hill Community Library, 60- 05 Main Street, Queens |
|
|
Final |
|
Consent Items |
Agenda
|
| Construction of a café kiosk and support building, Riverside Park South, Westside Highway, West 70th Street and Pier I, Manhattan |
|
|
Preliminary |
|
Public Hearing |
Agenda
|
| Reconstruction of the Bronx River Greenway, including the construction of four pedestrian bridges, Bronx River between Westchester Avenue and East 177th Street, Bronx |
|
|
Final |
|
Public Hearing |
Agenda
|
| Construction of a comfort station as part of Phase I, Ferry Point Park, East of the Whitestone Bridge, Balcom Avenue and Schley Avenue, Bronx |
|
|
Preliminary |
|
Public Hearing |
Agenda
|
| Construction of a visitor center, Brooklyn Botanic Garden, 1000 Washington Avenue, Brooklyn |
|
|
Final |
|
Public Hearing |
Agenda
|
| Construction of a dog run as part of Phase I, East River Waterfront, Wall Street to Maiden Lane, Manhattan |
|
|
Preliminary and Final |
|
Public Hearing |
Agenda
|
| Reconstruction of Pier 15 as part of Phase II, East River Waterfront, Wall Street to Rutgers Slip, Manhattan |
|
|
Preliminary |
|
Public Hearing |
Agenda
|